Project Summary |
Transportation System: INTRASTATE STATE HIGHWAY | District 03 - Wakulla County |
|
Description: SR 30 (US 98) FROM W OF WAKULLA RIVER BR TO SR 267 BLOXHAM CUTOFF RD | |
|
|
|
|
|
Construction Contract Information
Notice to
Proceed
Date |
Work
Begun
Date |
Present
Contract
Days |
Contract
Days
Used |
Percent
Days
Used |
01/11/2024
|
01/22/2024
|
330
|
91
|
27.58%
|
Vendor Name: M OF TALLAHASSEE, INC. |
|
|
Project Detail |
Fiscal Year: | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 |
Highways/Preliminary Engineering | (On-Going) |
|
Amount: |
$9,538
|
|
|
|
|
|
Highways/Construction | (On-Going) |
|
Amount: |
$4,664,597
|
|
|
|
|
|
|
Item Total: | $4,674,135 | | | | | |